Searching over 5,500,000 cases.


searching
Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.

American Towers LLC v. Bpi, Inc.

United States District Court, E.D. Kentucky, Southern Division, Pikeville

August 4, 2014

AMERICAN TOWERS LLC, Plaintiff,
v.
BPI, INC., et al., Defendants.

MEMORANDUM OPINION AND ORDER

AMUL R. THAPAR, District Judge.

When construction projects go awry, the resulting civil litigation is often as jumbled as the marred structure. The parties usually dispute what caused the project to fail, and causation is a fact-bound inquiry. Both parties then present expert testimony tending to show that the cause they prefer was, in truth, the culprit. Courts are ill-equipped to resolve disputes between experts about critical facts, and at the summary judgment stage, courts are not authorized to do so. So it should come as no surprise that the heavily factual dispute between the parties here must proceed to trial.

BACKGROUND

American Towers LLC operates wireless and broadcast communications sites around the country. R. 139-1 ¶ 4. After conferring with one of its customers, American Towers decided to erect a cell tower in Prestonsburg, Kentucky. R. 134 at 18; R. 139-5 at 4. Its plans also called for the construction of a tower compound and an access road, leading up a hill to the cell tower. R. 134 at 19-20; R. 139-5 at 4. American Towers accepted bids for the project from general contractors. Id. at 18-20. American Towers selected the bid of BPI, Inc., the companies executed a Master Contractor Agreement (the "agreement" or the "contract"), and BPI began building. See R. 138-2; R. 134 at 19-20.

After breaking ground on the project, BPI encountered what it regarded as a problem with American Towers' plans. R. 134 at 74. BPI thought the road's design was flawed. Id. The agreement imagined just such a scenario. If BPI recognized a problem, it was to stop work immediately, inform American Towers, and American Towers would then instruct BPI on how to proceed. Agreement § 1.4. BPI therefore stopped work on the road and told American Towers about the problem. R. 134 at 74. BPI also proposed a solution to the problem-a modification of the road's shape-and American Towers approved. Id. at 74-75. BPI then resumed construction in accordance with its new plan.

Alas, the solution was no solution at all. Less than one year later, the road BPI constructed collapsed in a landslide, damaging surrounding property and leaving the tower compound inaccessible and useless. R. 132 at 40-43; R. 134 at 23. The result was a flurry of litigation. American Towers sued BPI, alleging that BPI breached the agreement. BPI sued its subcontractors, the subcontractors sued each other, and everybody sued the insurer. After discovery, there were nearly as many motions for summary judgment as parties. This order deals with American Towers' and BPI's cross-motions for summary judgment only. See R. 138; R. 139. For the reasons explained below, this matter must proceed to trial, and both parties' motions for summary judgment are denied.

DISCUSSION

Summary judgment is appropriate where there is no genuine dispute as to any material fact. Fed.R.Civ.P. 56(a). When determining whether such a dispute exists, the Court must view the facts in the light most favorable to the non-moving party. Scott v. Harris, 550 U.S. 372, 378 (2007). If-viewed from that angle-the evidence is such that a reasonable finder of fact could return a verdict for the non-moving party, then the Court cannot grant summary judgment. Cordell v. McKinney, No. 13-4203, 2014 WL 3455556, at *4 (6th Cir. July 16, 2014).

Because federal jurisdiction is premised on the diversity of the parties, the Court must apply Kentucky's substantive law. Garden City Osteopathic Hosp. v. HBE Corp., 55 F.3d 1126, 1130 (6th Cir. 1995). The elements of a breach of contract claim are: (1) the existence of a valid contract; (2) breach of the contract; and (3) damages or loss caused by the breach. Metro Louisville/Jefferson City Gov't v. Abma, 326 S.W.3d 1, 8 (Ky. Ct. App. 2009).

I. BPI Is Not Entitled To Summary Judgment, Because The Contract Does Not Assign The Obligation To Consult A Design Engineer To American Towers Only.

BPI's main argument is that the contract required American Towers-not BPI-to consult a design engineer after BPI reported problems with the original design of the road. R. 138-1 at 14-16. BPI traces American Towers' supposedly sole responsibility for consulting a design engineer to the agreement's division of labor. The contract contemplated that American Towers would provide BPI with "drawings, specifications, " and "instructions." Agreement § 1.4. BPI, on the other hand, was responsible for "all construction means, methods, techniques, sequences and procedures...." Agreement § 4.1.1. The contract provided that BPI would complete its tasks in a "workmanlike manner and with the highest degree of skill and care exercised by reputable contractors performing the same or similar services...." Id. The idea, BPI says, is that American Towers was responsible for formulating the overall plan and design, and BPI was responsible for executing the plan precisely. Because consulting a design engineer is part of crafting the design-not part of executing the design-the responsibility to do so belonged to American Towers.

BPI says that the critical portion of the agreement confirms its interpretation. After BPI informed American Towers that it thought the road was poorly designed, the agreement required American Towers to "issue written instructions" about how to proceed to BPI. Agreement § 1.4. BPI says that its obligation was merely to execute whatever plan American Towers gave it, so American Towers was obliged to consult a design engineer before telling BPI what to do. American Towers therefore must bear the consequences, BPI says, of its own failure.

This argument glosses over key facts that weigh against BPI. True, when BPI encountered a problem, the contract required only that BPI inform American Towers and wait for instructions. Agreement § 1.4. But BPI apparently did more than the contract required. BPI proposed a new plan to American Towers, which American Towers approved, and which BPI proceeded to implement. R. 134 at 74. Dr. Ihab Saad, an expert witness, submitted a report explaining that BPI's vow to complete its work with "the highest degree of skill and care" exercised by similar contractors required it to consult a design engineer before proposing the new plan to American Towers. R. 139-7 at 54-56. Expert testimony is admissible to elucidate a specialized standard of care for the finder of fact. Charter Foods Inc. v. Derek Eng'g of Ohio, Inc., Civil No. 09-06-ART, 2009 WL 4825150, at *5 (E.D. Ky. Dec. 11, 2009). Indeed, if the fact finder would not understand the standard absent such testimony, then an expert may be required. Id .; Boland-Maloney Lumber Co. v. Burnett, 302 S.W.3d 680, 686 (Ky. Ct. App. 2009). So, viewing the facts in the light most favorable to American Towers, a jury could find that BPI proposed the new plan to American Towers, and-if the jury credits Saad's testimony-that the contract required BPI to consult a design engineer before doing so.

BPI has one round left in the chamber. No matter, BPI says, that the contract may have required BPI to consult a design engineer before proposing its plan, because the contract required American Towers to "issue written instructions" after learning of the problem. And the word "instruction" requires American Towers to do something more than merely "accept" or "approve" BPI's proposal. R. 145 at 13. To ...


Buy This Entire Record For $7.95

Download the entire decision to receive the complete text, official citation,
docket number, dissents and concurrences, and footnotes for this case.

Learn more about what you receive with purchase of this case.